POS Checklist for New Restaurants: An Eight-Week Timeline Covering Menu Data, Installation, Training and Soft Opening
A new restaurant should start preparing its POS system about eight weeks before opening. Choose the system and confirm the hardware quantities first, lay the network cables and sockets while fitting-out is under way, then organise and enter the menu data, install the hardware and set up printing by station, test each payment method, train the staff, and finally use a soft opening to find problems and fix them. The most common mistake is leaving the POS until a week or two before opening, with the result that cables have to be run exposed, the menu cannot be tested in time, and staff face their first busy period before they are familiar with the system. A POS is not a tool that is needed only on opening day. It is tied closely to the fitting-out, the kitchen layout, the menu design and staffing. This guide goes through the work in order, week by week, covering what has to be done at each stage, the details that are easily missed, and what to check on opening day and in the first month.
Key takeaways
- Start eight weeks ahead: choosing a system, cabling, entering the menu, installation, testing, training and a soft opening all take time.
- Cabling has to be done before fitting-out is finished: miss that window and the only options are exposed cables or chasing the walls again.
- Menu data takes the most time: the earlier the menu is finalised, the more time there is for testing and training.
- Kitchen printing must be tested on site: what looks right in the office often turns out differently when walked through in the kitchen.
- Training must cover exceptions: amendments, voids, split bills and a printer that will not print need more practice than the smooth flow does.
- The purpose of a soft opening is to find problems: the time set aside afterwards for fixing them matters more than the soft opening itself.
- The timeline has to fit the licence: the actual opening date depends on licensing progress, so plan by counting backwards.
Contents
- Why the POS needs to be prepared early
- Overview of the eight-week POS timeline
- Weeks 8 to 7: define your needs and choose a system
- Weeks 6 to 5: arrange network and power alongside fitting-out
- Week 4: organise and enter the menu data
- Week 3: install the hardware and set up printing
- Week 2: test payments and the full workflow
- Week 1: staff training
- Soft opening: go looking for problems
- Arrangements for opening day
- Checks in the first month after opening
- Fitting POS preparation to licensing progress
- The POS budget at the opening stage
- Seven mistakes new restaurants make most often
- Frequently asked questions
Why the POS needs to be prepared early
Many owners of new restaurants put their energy into the site, the fitting-out, the licence and recruitment, and treat the POS system as "the last machine to buy". In fact the POS involves far more than buying hardware, and several of the tasks have to be completed at particular times.
Cabling has a time window
Printing by station needs network cables running from the cashier to every kitchen station. These are best laid before the ceiling, floor and walls are closed up. Once fitting-out is complete, adding cables means running them exposed or opening up finished work.
Menu setup takes longer than expected
Entering the menu into the system is more than typing. Every item needs a name, price and category, and has to be assigned to a station. Set meals need their choices and surcharge rules set up, and menus for different times of day have to be set up separately. The more complex the menu, the longer it takes, and after entry every item still has to be tested.
Staff need time to become familiar with it
The staff of a new restaurant come from different backgrounds and have used different systems. If they meet the system for the first time the day before opening, the first busy period will be a scramble, and guests' first impression will suffer badly.
Problems need to surface before opening
A printer in the wrong place, a station that does not receive its tickets, a set meal priced wrongly: problems like these are bound to appear. The only difference is whether they are found during the soft opening or on opening day with a full house.
Overview of the eight-week POS timeline
The table below is a reference timeline based on eight weeks. A smaller outlet with a simple menu can compress it; a larger restaurant or one with more stations should allow more time.
| When | Main work | Done when |
|---|---|---|
| Weeks 8 to 7 before opening | Define needs, meet suppliers, choose a system | The system and hardware list are confirmed |
| Weeks 6 to 5 before opening | Fix hardware positions, lay network cables and allow for sockets | A network cable and power reach every position |
| Week 4 before opening | Finalise the menu, organise the data, enter it in the system | All items, prices, categories and set meals are entered |
| Week 3 before opening | Install hardware, set up each station's printer, test printing on site | Each station receives only its own tickets |
| Week 2 before opening | Test each payment method, rehearse the full workflow, check the daily closing | Everything from opening a table to daily closing runs without error |
| Week 1 before opening | Staff training, including how to handle exceptions | Every member of staff can carry out routine operations unaided |
| A few days before opening | Soft opening, followed by time set aside for fixes | Every problem found in the soft opening has been dealt with |
| First month after opening | Review reports, adjust the menu and staffing | The workflow is stable and the data is being used for decisions |
What if you have less than eight weeks?
If opening is already less than eight weeks away, deal first with the items that cannot be put off. The first is cabling, which should be confirmed with the fitting-out contractor at once. The second is finalising and entering the menu. The third is testing the printing and training the staff. Functions that are not essential on day one, such as membership, reservations and inventory, can be left until operations have settled.
Weeks 8 to 7: define your needs and choose a system
The aim at this stage is to decide which system to use and arrive at an accurate hardware list.
Write down the workflow first
From the guest sitting down to leaving, write down who handles each step and where. Who takes the order? At the cashier or at the table? Which stations do orders go to? How is the bill settled? Is there takeaway and collection? This workflow is the basis for choosing a system and configuring the hardware.
List the functions you need
Sort functions into three groups: essential on day one, needed within three months, and to be considered later. What is generally essential on day one is only ordering, printing by station, settlement and basic reports; the rest can follow step by step. For the overall buying criteria, see the complete guide to choosing a restaurant POS system.
Count the hardware
Work out the hardware from the number of cashier positions and kitchen stations: one POS terminal, one receipt printer and one cash drawer for each cashier position, and one kitchen printer for each station that needs its own ticket. For the full method and a worksheet, see the POS hardware checklist.
Information to prepare before meeting suppliers
- Type of restaurant and service model
- Number of seats and tables
- Floor plan of the premises, marking the cashier and each kitchen station
- A draft menu, including at least the categories and set-meal structure
- Expected opening date and fitting-out progress
- Whether tableside ordering, membership, reservations or inventory functions are needed
Questions to put to the supplier at this stage
- How long does it take from signing to being ready to use?
- Is on-site installation provided? Who is responsible for cabling?
- Who enters the menu? Is there a separate charge?
- How many training sessions are there, for whom, and in what form?
- How can support be obtained on opening day and in the first week if problems arise?
- What does maintenance cover? Is a loan unit available if hardware fails?
For how each charge is calculated, see the full analysis of restaurant POS pricing.
Weeks 6 to 5: arrange network and power alongside fitting-out
This is the stage in the whole timeline that must not be missed. If network cables and sockets are dealt with only after fitting-out is complete, both the cost and the result suffer considerably.
Mark the position of every piece of hardware on the floor plan
Mark the POS terminal, receipt printer, cash drawer, each station's kitchen printer and the network equipment on the floor plan one by one, and give it to the fitting-out contractor and the POS supplier to confirm. Only when the positions are fixed can cable lengths and routes be worked out.
Consider kitchen printer positions together with the kitchen equipment
The printer should be within the chef's reach and away from the stoves, the steam cabinet and the dishwashing area. Its position can therefore be decided only once the layout of the kitchen equipment is settled, and the cables should be laid before the equipment is brought in.
Arranging network cables and sockets
- One network cable per position: run from the network equipment to every device on the wired network.
- Allow spares: run one or two extra cables at the cashier and in the kitchen, so that adding equipment later needs no further work.
- Avoid heat and damp: cables in the kitchen are best protected by trunking and kept away from heat sources.
- Label both ends: it saves a great deal of time when tracing a fault later.
- Enough sockets: allow for the amount of hardware, to avoid chaining extension leads later.
- A separate circuit: avoid sharing a circuit with high-powered kitchen equipment.
Allow time for the broadband application
Business broadband takes time from application to installation, and some buildings and shopping centres have additional arrangements. Apply at this stage and confirm that the installation date falls before the POS hardware is installed. If you intend to use functions that need the internet, such as QR code ordering or electronic payment, a stable network is especially important.
Who is responsible for cabling?
Cabling may be done by the fitting-out contractor, the telecommunications provider or the POS supplier, and practice varies. Whoever does the work, ask the POS supplier for its cabling requirements and have them checked on site before the walls and ceiling are closed. The division of responsibility should be made clear at this stage, so that you do not discover just before opening that nobody has dealt with it.
Week 4: organise and enter the menu data
Menu data is the most time-consuming and error-prone part of POS preparation. The more clearly the data is organised, the more smoothly entry and testing will go.
Finalise the menu first
The menu should be broadly finalised by this stage. It can of course be changed later, but if it keeps changing during entry, testing cannot begin. You can fix the category structure, set-meal rules and prices first, and fine-tune the names of individual dishes afterwards.
Menu data worksheet
Organise the menu into a worksheet with the columns below and give it to whoever is entering the data. With every column filled in, there is no need to go back and forth with questions during entry.
| Column | Content | Points to note |
|---|---|---|
| Category | For example rice dishes, noodles, snacks, drinks | Group items the way staff think when ordering, not by copying the printed menu |
| Item name | The name shown on screen and on the kitchen ticket | Keep it short, so the kitchen understands it at a glance |
| Price | Dine-in price; list the takeaway price separately if different | Check item by item against the printed menu |
| Ticket station | Hot kitchen, cold kitchen, drinks bar and so on | Every item must be assigned |
| Options | Hot or cold, sweetness, portion, toppings and so on | State which carry a surcharge and how much |
| Set-meal structure | The main dishes, accompaniments and drinks that can be chosen | How many items per group, and the surcharge rules for switching |
| Serving period | Breakfast, lunch, afternoon tea, dinner | State the start and end time of each period |
| Charging rules | Service charge, tea charge, discounts | Whether a service charge applies to takeaway |
Other setup data to prepare besides the menu
- Table numbers and areas: the number, seats and area for every table.
- Staff accounts and permissions: who may take orders, void dishes, give discounts and view reports.
- Receipt details: shop name, address, phone number and anything else to be printed on the receipt.
- Payment methods: which are accepted and how each is recorded.
- Common remarks: no spring onion, less rice, extra spicy and the like, set up as buttons to cut down on typing.
Prepare test orders
Write out about ten representative orders in advance for the testing and training that follow. They should include the simplest order, the one with the most options, an order spanning several stations, a set meal with surcharges, a takeaway order, and cases that call for sharing a table, transferring a table, voiding a dish and splitting the bill. For how to set up cha chaan teng set meals, see the cha chaan teng POS buying guide.
Week 3: install the hardware and set up printing
With fitting-out nearly finished and the kitchen equipment in place, the POS hardware can be installed. The focus at this stage is confirming on site that every ticket reaches the right station.
Installing the hardware
Install the POS terminal, printers, cash drawer and network equipment in the positions marked earlier, and tidy the cables. Lay out the cashier so that it is comfortable for staff to operate: the POS terminal directly in front, the receipt printer on the dominant-hand side, and the cash drawer below or beside it.
Setting up each station's printer
Every printer has a setting name in the system, which the system uses to decide which items go to which printer. In the HKTC restaurant system, printer setting names are managed in the back-office management interface, and orders reach the right printer only when the name is set correctly. For the system's functions, see the restaurant POS feature overview.
Choosing the right type of printer
The cashier and the drinks bar generally use a thermal printer, such as the EPSON TM-88IV. The hot, steamy kitchen more often uses an impact printer, such as the EPSON TM-U220. For the differences between the two, see the kitchen printer buying guide.
Testing printing on site in the kitchen
Ask the kitchen chefs to stand at their own positions while the floor places a few test orders, and confirm each of the following:
- Each station receives only the items it has to make
- The type on the ticket can be read clearly at working distance
- Special requests stand out
- The table number and the dine-in or takeaway marking are clear
- The printer is placed where tickets are easy to take and it does not get in the way
- No tickets are missed when several orders are placed in a row
Testing what happens when a printer fails
Switch off one printer or remove its paper roll on purpose, watch how the system responds, and make sure staff know what to do. For the steps to check when a printer will not print, see troubleshooting a kitchen printer that is not printing.
Week 2: test payments and the full workflow
Once the hardware and printing are confirmed, test settlement and the complete workflow from start to finish.
Test each payment method for real
Every payment method you intend to accept should be tested once with a real transaction, and the way the payment is recorded confirmed. Electronic payment services have to be applied for separately with a payment service provider. Approval and installation take time, so apply early and confirm that the payment equipment will be in place before opening. The HKTC restaurant system supports front-of-house settlement and smart IC card settlement; if you need other payment methods, please say so when you enquire. For how the different payment methods are arranged, see the guide to connecting e-payment to your restaurant POS.
Full workflow rehearsal
Using the test orders prepared earlier, go through the complete workflow starting from opening a table:
- Open a table and place an order
- Confirm that each station prints correctly
- Add to the order
- Amend one item
- Void one item
- Transfer the table
- Open a shared bill on the same table
- Split the bill and settle the parts separately
- Settle with different payment methods
- Confirm that the cash drawer opens and the receipt is correct
Illustrated instructions for each operation are in the user manual.
Checking the daily closing report
After the test transactions, run a daily closing and check whether the total sales, the amount for each payment method and the record of voids on the report match the transactions just made. Any discrepancy in the daily closing should be resolved before opening. For how to read the reports, see the guide to reading POS reports.
Clearing the test data
Confirm with the supplier how test transactions should be handled, so that test data does not find its way into the reports after opening.
Week 1: staff training
Staff training should not teach only the flow where everything goes to plan. What really throws a new restaurant into confusion is usually the exceptions.
Training content
| Who | Routine operations | Exceptions |
|---|---|---|
| Floor staff | Opening tables, ordering, adding to orders, sharing and transferring tables | Wrong orders, guests changing their minds, sold-out dishes |
| Cashier | Settlement, each payment method, giving change | Split bills, refunds, failed payments, a cash drawer that will not open |
| Kitchen and drinks bar | Reading kitchen tickets, changing paper and ribbons | A printer that will not print, faded print, receiving tickets that belong to another station |
| Manager | Operations requiring authority, daily closing, viewing reports | What to do when the system fails, contacting technical support |
Define permissions clearly
Make clear during training which operations staff may handle themselves and which must go to the manager. Operations that involve money, such as voiding dishes, giving discounts and cancelling orders, should require authority and leave a record. The HKTC restaurant system has controls at three stages (settlement, ordering and voiding). No sales data can be erased; it can only be processed as a return or exchange, and an operation trail is recorded.
How to train
- Practise with the real menu: use the restaurant's actual menu and test orders, not demonstration data.
- Everyone operates it themselves: watching is not enough; every member of staff must carry out every operation personally.
- Simulate a busy period: have several people place orders at once and practise operating under pressure.
- Produce a simple guide: write the most common operations and fault procedures on a single sheet and post it at the cashier and in the kitchen.
Prepare a fallback procedure
Power cuts, network outages and hardware faults can always happen. Have handwritten dockets and a calculator ready, and make sure every member of staff knows how to take orders, tell the kitchen and take payment when the system cannot be used, and how to enter the data into the system afterwards.
Soft opening: go looking for problems
The real purpose of a soft opening is to bring unexpected problems to light while the number of guests is under control. It should therefore not chase turnover. It should deliberately create the kinds of situation you will meet day to day.
Arranging the soft opening
You can invite family, friends and acquaintances and ask them to help with the testing. The seats need not all be filled, but there should be a period that simulates a busy service.
Soft opening test checklist
- Several tables ordering at the same time
- Amending and cancelling items after ordering
- Frequent add-on orders
- Transferring and sharing tables
- One table settling separately between several people
- Dine-in and takeaway orders arriving together
- Using every payment method
- The set meal with the most complicated options
- What happens when a dish sells out
- What happens when a printer runs out of paper
- Daily closing and checking the cash at the end of the day
Record every problem
Assign one person solely to record the problems that arise during the soft opening: which step is slow, which order goes wrong, where staff hesitate, where guests are kept waiting. However small the problem, write it down.
Set aside time for fixes afterwards
Leave at least one day between the soft opening and the official opening purely for dealing with problems: changing menu categories and button positions, adjusting which station each item goes to, revising permissions, and giving staff further training. That day is often worth as much as the soft opening itself.
Arrangements for opening day
Checks before opening the doors
- All POS terminals and printers are switched on and properly connected
- Every printer is loaded with enough paper, with spare rolls and ribbons within arm's reach
- A test ticket has been printed to confirm that each station is printing normally
- The cash drawer holds enough change
- The dishes on offer that day and any sold-out items have been updated
- Handwritten dockets and a calculator are at the cashier, ready for use
- Technical support contact details are posted at the cashier
Staffing
For the first few days, roster more staff than usual and assign one colleague who knows the system well to deal solely with POS problems, so that the others can concentrate on serving guests.
Technical support
Confirm the support arrangements for opening day with the supplier in advance, such as whether remote help can be given straight away. HKTC provides customers under contract and in their first year with free remote technical support and free loan of hardware with similar functions while hardware is being repaired. Terms are set out under maintenance and renewal. For how to handle common problems, see troubleshooting common problems and the guide to handling common POS faults.
The principle when problems arise
Minor problems on opening day are normal. The principle is to make sure first that guests' orders reach the kitchen and that bills are settled smoothly, switching to handwritten dockets at once if necessary. Leave the problem itself until after closing, and do not try to change system settings during a busy period.
Checks in the first month after opening
After opening, the role of the POS shifts from preparing to open to providing operating data. In the first month, do not look at turnover alone. The following figures matter just as much.
Figures worth watching
- Order volume by time period: for adjusting staff rosters.
- Best-selling and slowest-selling dishes: for adjusting the menu and preparation.
- Average amount per bill: for assessing pricing and set-meal design.
- Ratio of dine-in to takeaway: for adjusting packaging supplies and staff allocation.
- Number of voids and amendments: if this is on the high side, find out whether the cause lies in menu setup, staff operation or controls.
Adjustments to complete in the first month
- Rearrange menu buttons according to actual sales
- Delete or hide items that do not sell
- Add buttons for requests that are often typed in as remarks
- Review whether each member of staff's permissions are appropriate
- Give further training in the weaker areas
Switching on other functions step by step
Once operations have settled, functions such as membership, reservations and inventory management can be switched on as needed. The HKTC restaurant system brings these modules together in one system with shared data, so no additional software is needed.
Fitting POS preparation to licensing progress
To operate a restaurant in Hong Kong that sells meals for consumption on the premises, you must obtain a restaurant licence from the Food and Environmental Hygiene Department. The holder of a general restaurant licence may prepare and sell food by any method of cooking, while a light refreshment restaurant licence permits only simple methods of cooking that do not produce large amounts of greasy fumes. To help food businesses open early, the Department operates a provisional licence system and issues provisional licences, valid for six months, to premises that have met the basic health, building safety and fire safety requirements.
Plan by counting backwards
The actual opening date depends on licensing progress, which in turn is affected by plan approval and the completion of works, and cannot always be predicted accurately. The POS timeline is therefore best counted backwards from the expected opening date and adjusted when licensing progress changes. For the application procedure and the latest requirements, rely on the information published by the Department, or consult a professional adviser.
Where the licence and the POS affect each other
- Layout plans: the layout of the kitchen and seating is fixed when the licence is applied for, and the positions of the POS hardware should be planned from the same drawings.
- Number of seats: this affects the table numbering and the number of ordering devices.
- Method of cooking: this affects the menu, and through it the number of stations and printers.
- Sequence of works: cabling should follow the progress of the fitting-out and be finished before the walls and ceiling are closed.
The POS budget at the opening stage
A new restaurant is short of capital, so the POS budget should separate what is essential for opening from what can be added later.
| Item | Essential for opening | Can be added later |
|---|---|---|
| Software functions | Ordering, printing by station, settlement, basic reports | Membership, reservations, inventory |
| Hardware | POS terminal, receipt printer, kitchen printers, cash drawer | Extra ordering devices, display, scanner |
| Network and power | All cables and sockets, including spares | Should not be put off |
| Services | Installation, menu setup, training, first-year maintenance | Later retraining |
Where not to economise
Network cables and sockets should be done in full at one go, including those allowed for future expansion, because adding them afterwards costs far more than doing them during fitting-out. Nor should the number of kitchen printers be cut. Making several stations share one printer only slows service at busy times.
Compare plans on three-year total cost
When comparing suppliers, add up the software, hardware, installation, training and the charges from the second year onwards, and do not look at the first payment alone.
Seven mistakes new restaurants make most often
Leaving the POS until last
The supplier is contacted only a week or two before opening, so cabling, menu entry, testing and training are all crammed together, and there is no time to recover if any one of them goes wrong.
Cabling only after fitting-out is finished
The window before the walls and ceiling were closed has been missed, and the cables have to be run exposed, which looks poor and is easily damaged.
A menu that is never finalised
The menu keeps changing, so entry and testing cannot begin, and training has to make do with incomplete data.
Testing only in the office, never walking it through on site
A printing arrangement that looks sensible on paper turns out in the kitchen to have a printer in the wrong place or a station that receives no tickets.
Training only the smooth flow
Staff know how to place an order but not how to amend one, void a dish or split a bill, and are at a loss when a guest changes their mind.
No soft opening, or no time for fixes afterwards
The soft opening is treated as a rehearsal instead of a test, and there is no time to deal with the problems it reveals.
No fallback procedure
The whole restaurant stops as soon as the system fails. Handwritten dockets and clear contingency steps keep the impact to a minimum.
POS preparation for new restaurants: FAQs
How long before opening should a new restaurant prepare its POS system?
About eight weeks before opening is recommended. Choosing a system, cabling alongside fitting-out, organising and entering the menu, installing hardware, testing payments, training staff and holding a soft opening all take time. A small outlet with a simple menu can compress the schedule, but cabling must be finished before the walls and ceiling are closed.
When should the POS network cables be laid?
During fitting-out, before the ceiling and walls are closed. That is when running cables is easiest and neatest. Adding cables after fitting-out is complete means running them exposed or opening up finished work.
The menu is not finalised yet. Can the POS be installed first?
The hardware can be installed and the basic setup completed first, but the menu should be finalised as soon as possible. Entry and testing can begin only once the category structure, set-meal rules and prices are settled. A menu that keeps changing makes testing and training impossible.
How long does it take to enter the menu?
It depends on how complex the menu is. A menu made up mainly of à la carte items is quicker to complete; one with multi-layer set meals, many options and time-based menus takes longer, and every item still has to be tested after entry. Organising the menu into a clear worksheet shortens the time noticeably.
What should staff training cover?
Besides routine operations such as opening tables, ordering, adding to orders and settlement, it must cover exceptions such as amending orders, voiding dishes, transferring tables, sharing tables, splitting bills, refunds and a printer that will not print, and make clear which operations require the manager's authority.
What is a soft opening for?
Its purpose is to find problems while the number of guests is under control. Deliberately test situations such as simultaneous orders, amendments, split bills and every payment method, and leave at least one day afterwards to fix problems and give further training.
What if the POS has a problem on opening day?
First make sure that orders reach the kitchen and that guests can settle their bills smoothly, switching to handwritten dockets at once if necessary, and contact technical support. Do not try to change system settings during a busy period; leave the problem until after closing. Handwritten dockets should be prepared in advance and staff made familiar with the contingency steps.
Can the POS be installed before the restaurant licence is obtained?
Installing and testing the POS is part of the preparation before opening and generally goes on alongside the fitting-out. When you can actually start trading depends on the licence, and for the application procedure and requirements you should rely on the information published by the Food and Environmental Hygiene Department.
Does a new restaurant need membership and inventory functions from the start?
Not necessarily. What is essential on day one is ordering, printing by station, settlement and basic reports. Membership, reservations and inventory management can be switched on once operations have settled, so that staff become familiar with the basic operations first.
Can HKTC help a new restaurant prepare its POS?
Yes. HKTC supplies F&B POS software and hardware, with system setup and after-sales maintenance handled by the same team. Tell us your restaurant type, number of tables, and number of cashier positions and ticket stations, and we will recommend a system and hardware setup. Call +85294466816, email hktcsoft@gmail.com, or enquire through the Contact us page.
Summary: put the POS into the opening plan from day one
For a new restaurant, POS preparation comes down to time. Start eight weeks ahead and you can choose a system without rushing, lay the network and power while fitting-out is under way, organise the menu clearly and test it item by item, let staff practise for themselves before opening, and use a soft opening to find and fix problems. Leave the POS until last and every stage is squeezed, so that problems can only surface in front of guests on opening day. Putting the POS into the same plan as the site, the fitting-out, the licence and recruitment is an important step towards a smooth opening.
HKTC Digital Technology (Hong Kong) Limited supplies F&B POS software and hardware to Hong Kong restaurants, with system setup, hardware supply and after-sales maintenance all handled by the same team. If you are preparing to open, you are welcome to contact us early to discuss the system configuration and hardware positions. Call +85294466816 or reach us on WhatsApp, or visit us at 194 Reclamation Street, Yau Ma Tei, Hong Kong. You can also browse the feature overview, POS hardware products and client references first.